  • Back to Home

  • 中

  • A

  • RSS

Default Logo

  • About RB
    • About RB
      • Director General of RB
      • Organizational Outline of the Railway Bureau
      • Quality policy
      • ISO Area
    • Affiliated Units
      • Northern Engineering
      • Central Engineering
      • Southern Engineering
      • Eastern Engineering
  • Railway Construction
    • Project Management
      • Progress of Projects
    • en-路網建設
      • Double-track Electrification of Railways in Hualien-Taitung Area
      • South Pingtung Tourist Railway Project
      • Airport MRT Extension Line Project
      • Keelung MRT
      • Airport MRT Adding Airport Terminal 3 Station (A14) Project
    • en-鐵路立體化建設
      • Tainan Urban District Railway Underground Project
      • Taiwan Railway Pingzhen Temporary Station Construction Project
      • Taoyuan Metropolitan Area Railway Underground Project
      • Elevated Railway Project at the Urban Area of Chiayi
      • Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project)
      • Taiwan Railway Station Aesthetics and Functional Improvement Project – South Link Station
    • en-已完成
      • Taiwan Railway Fengming Temporary Station Construction Project
      • Taichung Metropolitan Area Elevated Railway Project
      • South-Link Line Railway Electrification Project
      • Hualien-Taitung Line Electrification Project
      • Hualien-Taitung Line Efficiency Improvement Project
      • Taichung Metropolitan MRT System Wuri-Wenxin-Beitun Line Construction Project
      • Access Road to HSR Station Area Project
      • HSR Project
      • Taiwan Taoyuan International Airport Access MRT System Construction Project
  • Railway Business
    • Technology Zone
      • High-Speed Rail Electromechanical System
      • Airport Access MRT System
      • Taiwan Railway System Electromechanical Subsystems
      • Technical Documents
    • Project Management
      • Quality Assurance
      • Occupational Safety and Health
    • Operation Supervision
      • Supervision regulations
      • Operation
      • Safety
      • Inspection
      • Investigation
    • Railway Industry
      • Industry Policies
      • Action Plan
      • Industry Development Subsidy
      • Important Activities and Achievements
      • Contact Information
      • Railway Designated product area
    • Station Development
      • Taiwan High Speed Rail
      • Taoyuan Airport MRT
      • Investment Services
  • Publications
    • Multimedia
    • Newsroom
    • Major Policies
    • Public Information
      • Award Information
      • Awards Area
    • Laws and Regulations
    • Integrity Platform
      • Launching Ceremony
      • Contact Meeting
    • Gender Mainstreaming
  • Service
    • Downloads
      • ISO File Download
    • Employee Services
    • Online Application
      • High-Speed Rail Corridor Cable Trays
      • High-Speed Rail Station External Pre-embedded Pipelines
      • Taiwan Fiber-optic Cable Corridor
  • en-範例
    • en-子選單
      • en-單一文章
      • en-文章列表
      • en-頁籤
      • en-計畫列表
      • en-台灣地圖-圖片
      • en-台灣地圖-MAP
      • en-檔案下載-通用
      • en-檔案下載-法令
      • en-線上申辦
      • en-電子書
:::
Home
Railway Construction
en-鐵路立體化建設
Taiwan Railway Pingzhen Temporary Station Construction Project

  

Taiwan Railway Pingzhen Temporary Station Construction Project


4 Phases of Construction
1. Study
2. Design
3. Construction
4. Completion
Plan Status

Planned
1%

Actual
10%

Progress
+9%

Go toCurrent statusCurrent
4. Completion
無內容
View more>>
3. Construction
無內容
View more>>
2. Design
無內容
View more>>
1. Study
無內容
View more>>
Plan Introduction


The origin of the project

In order for th e metropolitan area to enjoy MRT-oriented railway   transportation   servic es,   Taiwan   Railway Administration planned to add Pingzhen Station when it
promoted the "Ta iwan Railway Rapi d Transit Systematization" in 2004. Later, due to some reasons, it has not been completed, and it has been included in the Taoyuan Railway Undergroun d Project.
In order to open to public in Pingzhen area as soon as possible to meet th e needs of the public, the Executive Yuan held a review meeting for the report of Additional Taiwa n Railway Fengming Temporary Station Project on September 18, 2019. The conclusion is abbreviated as fol low: As mentioned by th e Taoyuan City Government, the Exec utive Yuan also approved the addition of Pingzhen Station in 2005. It is also the construction that the government has already promised to implement and is currently included in th e scope of th e railway underground project. The Ministry of Transportation and Communications is requested to immediately apply for the construction of the Pingzhen Temporary Station in line with fairness. Therefore, the Railway Bureau launched the plan to report for approval according to the instructions. Then, it was approved by the Executive Yuan with the l etter No. 1090024463 on August 3, 2020.

 

Project outline

  • Project period: August2020 to May 2026.
  • Project scope: The starting point of the route is about 68K+520, and the ending point is about 69K+360. The total length is about 840 meters.
  • Construction content: The type of station is planned as the calling station. There are two side platforms with 3m in width and 220m in length.
  • Program funding: NT$497.16 million.
  • Project location: Taoyuan City.
  • Project schematic diagram:

 

 

expected benefit

  • Before the undergrounding of the railway, a temporary station will be added first, which can be used by the public early, fulfilling the government's early promise, and can also assist in the diversion of transportation at Zhongli Station and the relief of surrounding traffic.
  • Achieve the goal of railway rapid transit systematization and solve the commuting needs of metropolitan areas.
  • Attract private vehicles to take Taiwan Railway, indirectly reducing carbon dioxide emissions and air pollution.

The origin of the project

In order for th e metropolitan area to enjoy MRT-oriented railway   transportation   servic es,   Taiwan   Railway Administration planned to add Pingzhen Station when it
promoted the "Ta iwan Railway Rapi d Transit Systematization" in 2004. Later, due to some reasons, it has not been completed, and it has been included in the Taoyuan Railway Undergroun d Project.
In order to open to public in Pingzhen area as soon as possible to meet th e needs of the public, the Executive Yuan held a review meeting for the report of Additional Taiwa n Railway Fengming Temporary Station Project on September 18, 2019. The conclusion is abbreviated as fol low: As mentioned by th e Taoyuan City Government, the Exec utive Yuan also approved the addition of Pingzhen Station in 2005. It is also the construction that the government has already promised to implement and is currently included in th e scope of th e railway underground project. The Ministry of Transportation and Communications is requested to immediately apply for the construction of the Pingzhen Temporary Station in line with fairness. Therefore, the Railway Bureau launched the plan to report for approval according to the instructions. Then, it was approved by the Executive Yuan with the l etter No. 1090024463 on August 3, 2020.

 

Project outline

  • Project period: August2020 to May 2026.
  • Project scope: The starting point of the route is about 68K+520, and the ending point is about 69K+360. The total length is about 840 meters.
  • Construction content: The type of station is planned as the calling station. There are two side platforms with 3m in width and 220m in length.
  • Program funding: NT$497.16 million.
  • Project location: Taoyuan City.
  • Project schematic diagram:

 

 

expected benefit

  • Before the undergrounding of the railway, a temporary station will be added first, which can be used by the public early, fulfilling the government's early promise, and can also assist in the diversion of transportation at Zhongli Station and the relief of surrounding traffic.
  • Achieve the goal of railway rapid transit systematization and solve the commuting needs of metropolitan areas.
  • Attract private vehicles to take Taiwan Railway, indirectly reducing carbon dioxide emissions and air pollution.
:::
  • About RB
    • About RB
    • Affiliated Units
  • Railway Construction
    • Project Management
    • en-路網建設
    • en-鐵路立體化建設
    • en-已完成
  • Railway Business
    • Technology Zone
    • Project Management
    • Operation Supervision
    • Railway Industry
    • Station Development
  • Publications
    • Multimedia
    • Newsroom
    • Major Policies
    • Public Information
    • Laws and Regulations
    • Integrity Platform
    • Gender Mainstreaming
  • Service
    • Downloads
    • Employee Services
    • Online Application
  • en-範例
    • en-子選單
  • Privacy Policy  |
  • Information Security Policy  |
  • Open Announcement
logo

Emergency Contact: During Office Hours: (02)8072-3333 | After Hours or Holidays: (02)8969-1601 Railway Bureau, MOTC All Rights Reserved | Tel: (02)8072-3333 | Fax: (02)8969-1567 Address: 9F., No.7, Sec. 2, Xianmin Blvd., Banqiao Dist., New Taipei City 220231, Taiwan (R.O.C.)

Ethics Hotline: (02)8969-1540 | Ethics Fax: (02)8969-1539 Ethics Mailbox: New Taipei City Government Post Office Box 18 Ethics Email: invx@rb.gov.tw Recommended browsers: Chrome, Edge, Safari, Firefox. Screen resolution: 1280 X 810 or higher.

logo